Re: Re: Domain Interchage / Anzac station - more pics
  Stuart Keenan

Yuri is not mistaken, Caulfield station is due to see major work in January
which will further reduce some of the routing options there.

Just this morning in the middle of the peak, a fault saw some Frankston
bound trains run via the Local lines and platform 4 at Caulfield. That
option won't be available after the works.

Stuart

On Mon, Dec 5, 2022, 10:26 Mal Rowe mal.rowe@...> wrote:

> Here are some more pics from Vincent Chan's 'eye in the sky':

>

> The night pic of 4 December shows the concrete pour (to sleeper height)

> in progress.

>

> The 'Filling' pic shows the crushed concrete being spread on 5 Dec -

> this morning. It will be rolled in to just below rail height.

>

> Final Pic looks across towards Domain Rd. The actual road is between

> the trees and the buildings at right and is covered with construction

> sheds.

>

> The closest track leads to Park St, next track is the 'mainline' north

> up St Kilda Rd, first track behind the big vent shafts is the southbound

> 'mainline' and trck beyond that is the track leading to Domain Rd.

>

> You can see that the crushed concrete fill is in place at left on the

> closest track.

>

> Mal Rowe - looking forward to a ride in a couple of weeks

>

> --

> You received this message because you are subscribed to the Google Groups

> "TramsDownUnder" group.

> To unsubscribe from this group and stop receiving emails from it, send an

> email totramsdownunder+unsubscribe@....

> To view this discussion on the web visit

> https://groups.google.com/d/msgid/tramsdownunder/0e04ef79-4f1a-d497-5adb-e3e377dc6525%40gmail.com

> .

>