Re: Re: L1 LIGHT RAIL TRACKWORK 19-24 NOVEMBER
  Mal Rowe

On 21/11/2022 14:31, Greg Sutherland wrote:
> How long would Yarra Trams have allowed for this type and scope of

> work to be undertaken in Melbourne, especially given that Yarra would

> have undetaken such work by the engagement of contractors?


Replacing a couple of hundred metres of track in Spring St, including
the junction at Bourke St took 7 days. See: https://tdu.to/i/72692

That was extra fast as they didn't want to upset the pollies, but I
would assume that the Sydney location would also be time sensitive.

Mal Rowe - still wondering how the first replacement of track layed
using the current method will be renewed.