Re: Extra trains for NSW ‘on hold’ amid warning of investment slump
  TP

Obviously poor old Granny is running out of "scandals". Have they noticed
that, after the current orders are fully delivered, NSW basically has all
the rolling stock it needs until the next round of lifecycle replacements?
New country fleet locked in and in progress, interurbans largely completed,
suburbans completed, metro second batches in progress, trams second batches
in progress. Anything further beyond these is obviously waiting to see
where the patterns of patronage land post-pandemic.

Tony P

On Thursday, 18 August 2022 at 13:55:54 UTC+10gregsut...@...
wrote:

>

> https://www.smh.com.au/national/nsw/extra-trains-for-nsw-on-hold-amid-warning-of-investment-slump-20220809-p5b8dl.html

> Extra trains for NSW ‘on hold’ amid warning of investment slump

> [image: Matt O'Sullivan]

> By Matt O'Sullivan https://www.smh.com.au/by/matt-o'sullivan-hvehy

> August 18, 2022 — 5.00am

> Key points

>

> - A strategic report by the state-owned Transport Asset Holding Entity

> warns that its investment plan “tails off significantly” after 2025 to

> about $500 million annually.

> - The “sensitive” report couches the “lack of future investment and

> funding” as both a “challenge and an opportunity” for TAHE.

> - Fixing corroded steel over-bridges in regional areas is one of the

> “major challenges” the government is grappling with in maintaining the

> heavy rail network.

> - A government spokeswoman said more than $5.3 billion was being

> invested through digital systems, infrastructure upgrades and new trains.

> - Labor’s transport spokeswoman said there was a “real danger” that

> passengers would end up with second-class services if the government cut

> investment.

>

> Advertisement

>

> The NSW government has delayed long-term plans to buy extra passenger

> trains as internal documents warn that investment in the existing network

> will slump within the next few years.

>

> The strategic report by the state-owned Transport Asset Holding Entity

> (TAHE) warns that its investment plan “tails off significantly” after 2025

> to about $500 million annually, a sum which will largely be spent on

> maintenance.

> [image: Confidential documents show the government has put “on hold”

> buying extra passenger trains beyond the existing commitments it has made.]

>

> Confidential documents show the government has put “on hold” buying extra

> passenger trains beyond the existing commitments it has made.Credit:Brook

> Mitchell

>

> It also shows that fixing corroded steel over-bridges in regional areas is

> one of the “major challenges” the government is grappling with in

> maintaining the state’s heavy rail network.

>

> The purchase of extra passenger trains is “on hold” beyond existing

> commitments in a project known as “more trains, more services”, according

> to the report, until there is greater certainty about patronage on the rail

> network, which took a hit during the pandemic.

>

> The latest part of the “more trains, more services” project, which will be

> delivered, includes the purchase of an extra 56 train carriages for

> intercity services as well as a batch of new Waratah suburban trains. It

> also involves an upgrade to a rail maintenance facility on the Central

> Coast.

> Related Article

> [image: An artist’s impression of the new Spanish-built regional trains.]

>

> https://www.smh.com.au/national/nsw/another-multibillion-dollar-nsw-train-project-at-risk-of-delays-cost-overruns-20220629-p5axs0.html

> Exclusive Public transport

> https://www.smh.com.au/topic/public-transport-610

> Another multibillion-dollar NSW train project at risk of delays, cost

> overruns

> https://www.smh.com.au/national/nsw/another-multibillion-dollar-nsw-train-project-at-risk-of-delays-cost-overruns-20220629-p5axs0.html

>

> The “sensitive” report – completed in December – couches the “lack of

> future investment and funding” as both a “challenge and an opportunity” for

> TAHE.

>

> It says that “balancing and prioritising” future investment in the

> transport network with “TAHE-led commercial development is a critical area

> of focus”.

>

> The *Herald* recently revealed TAHE’s ambitious plan

> https://www.smh.com.au/national/nsw/secret-plans-to-sell-rezone-and-develop-land-across-sydney-railways-20220614-p5atiw.html

> to sell or redevelop land across Sydney’s rail network and morphing into a

> big property developer to deliver more than $40 billion in government

> windfalls.

> Advertisement

>

> The warning about a looming drop in investment comes as the government has put

> on ice

> https://www.smh.com.au/politics/nsw/nsw-told-to-put-high-profile-road-transport-projects-on-ice-20220530-p5app7.html

> several large transport projects, including the Beaches Link motorway

> tunnel

> https://www.smh.com.au/national/nsw/lives-in-limbo-as-north-sydney-s-divisive-beaches-link-tunnel-stalls-20220602-p5aqp6.html

> in Sydney’s northeast.

>

> Labor transport spokeswoman Jo Haylen said there was a “real danger” that

> train passengers across NSW would end up with second-class services if the

> government cut investment.

> [image: One of the intercity trains at the centre of a stand-off between

> rail unions and the NSW government.]

>

> One of the intercity trains at the centre of a stand-off between rail

> unions and the NSW government.Credit:Tom Rabe

>

> “Any cuts will lead to fewer trains, fewer services, and to our rail

> infrastructure becoming obsolete and unsafe,” she said.

>

> A government spokeswoman said more than $5.3 billion was being invested in

> the “more trains, more services” program to deliver a range of benefits for

> rail customers through digital systems, infrastructure upgrades and new

> trains.

>

> She said the new intercity fleet would be progressively introduced on the

> Central Coast and Newcastle line once an operating model was finalised and

> crews trained. A timeline for them starting services on the Blue Mountains

> and South Coast lines would be determined after more trains were delivered

> and further testing completed.

> Related Article

> [image: Car emissions are the subject of a new industry campaign.]

>

> https://www.smh.com.au/national/revealed-car-industry-s-secret-emissions-plan-would-slow-electric-vehicle-uptake-20220805-p5b7pe.html

> Exclusive Electric cars https://www.smh.com.au/topic/electric-cars-1mqf

> Revealed: Car industry’s secret emissions plan would slow electric vehicle

> uptake

> https://www.smh.com.au/national/revealed-car-industry-s-secret-emissions-plan-would-slow-electric-vehicle-uptake-20220805-p5b7pe.html

>

> The new intercity trains

> https://www.smh.com.au/national/nsw/negotiation-breakdown-threatens-to-keep-new-rail-fleet-in-mothballs-20220608-p5as9q.html

> remain at the centre of a prolonged dispute between unions and the

> government, which has resulted in months of various forms of industrial

> action

> https://www.smh.com.au/national/nsw/last-train-to-bondi-has-ripple-effect-on-small-businesses-commuters-20220810-p5b8p0.html

> by rail workers.

>

> The confidential report by TAHE also warns that maintenance of

> over-bridges on rail lines in regional areas “continues to be one of the

> major challenges”.

>

> “Severe corrosion to structural members and fastenings is the primary

> concern for the steel over-bridges. The load rating investigation projects

> are underway and there is an increase in over-bridges with load

> restrictions,” it says.

>

> In comparison, the overall condition of bridges and other infrastructure

> on Sydney’s metropolitan rail network is deemed “average”.

>

> Regional Transport Minister Sam Farraway said he had “full confidence”

> that the state’s country rail network was “well maintained”.

>

>

>

>