G'day all, I braved the rain last Wednesday to update the works in North
Parramatta.
Fences and barricades are being removed and some streets are reopened to
traffic.
New signals have been installed in O'Connell St & New / Fleet Sts near
Cumberland Hospital stop.
Grass has been laid in the wire free section west of the stop. Landscaping
is in, traffic lanes paved and lines marked. Road signs installed and
generally everything cleaned up. Tram stop platforms are in but the
shelters are yet to come. All we need now is the Trams !
I've attached a few pics.
3588: Looking down Factory St.
3590: Looking up Factory St.
3594: Turning into Church St.
3596: Factory St stop (in Church St)
3610: Fennell St stop. " " " "
3617: Prince Alfred Sq stop " " "
3623: Lennox Bridge.
Regards,
Tim, in soggy Sydney