Re: DDA compliance and Melbourne trams - VAGO report
  Robert Smith

With a reduction in the number of stops, their is ~500 stop pairs to be
replaced in 26 months, with only 7 done this year 6 of which were funded by
the last Lib Government for the route 96 project

On Sunday, 29 November 2020 at 12:08:08 pm UTC+11 Robert Smith wrote:

> I saw somewhere else, the cost of adding a low floor section to a B class

> was $2m 10 years ago, and was not worth it as they are due for retirement

> in the early 2030's

>

> On Saturday, 28 November 2020 at 6:33:48 pm UTC+11

>transit...@... wrote:

>

>> A most interesting report. It does answer some questions that have been

>> raised in the last couple of days. It gives a total cost for replacement E

>> class trams, from which one gets the Cost of an E class is $6.99M/tram (271

>> high floor trams with replacements to cost $1.68B). It also gives a cost

>> for platform stops, at $1.27M/pair of stops. Whatever, the roll out of

>> level boarding stops is way behind what is needed. I am not certain what

>> the cost of the elevated track parallel to Sydney road is (who does?), but

>> I suspect that it is far more than the cost of replacing all the non-level

>> boarding stops. A Stop Rollout Strategy is to be produced by June 2021

>> (with luck!) which will cost $3.1M (funded in the 2019/20 budget). At that

>> date DOT have to replace 1215 stops (pairs? or singles?) by 31 Dec 2022. I

>> foresee the need for an exemption and extension.

>>

>> New Trams

>>

>> A most interesting section states:

>>

>> "DoT demonstrated to us how it plans to replace all high-floor trams with

>> low-floor trams by the 31 December 2032 DSAPT deadline. However, achieving

>> the target is contingent on DoT receiving sufficient funding to procure

>> another 255 low-floor trams (E-Class or Next Generation Tram or a mixture

>> of both) to replace 307 high floor trams on the network. DoT purchased 10

>> more E-Class trams in 2018 and received funding in 2019 for a further 10,

>> which will bring the total to 100 for this type of tram.

>>

>> DoT intends to replace 1.2 high-floor trams with one low-floor tram. This

>> means that to achieve the 31 December 2032 DSAPT requirement, DoT will need

>> to commission 28–30 low-floor trams per year from 2020 until 2029.

>>

>> *This rollout is ambitious and is more than double the current delivery

>> achievements for the E-Class tram.* The future delivery schedule also

>> needs to allow for required manufacturing time frames plus any extra

>> testing that may be required for a new class of tram like the Next

>> Generation Tram.

>>

>> Based on available evidence, it can take three to four years to

>> manufacture and commission a new tram, although DoT believes this lead time

>> could reduce after the selected manufacturer’s design and production

>> processes have matured, allowing for a ramp up in the rate of delivery part

>> way through a multi-year build program.

>>

>> To get the money required to build 255 low floor trams by 2032 is rather

>> like wishing that pigs might fly. We will shortly (?) get 100 E class - it

>> has taken 8 years (11/13 to some time in 2021, hopefully) to get 100 E

>> class. Deliveries should improve a bit with the guaranteed money for 100

>> in the budget, but even so, this means working 2 shifts for Bombardier.

>>

>> What the report did not mention was a need to think about replacing the C

>> class - 36 trams built 2001/2. While the Z and A and B cars are much

>> older, in general they are in 'fair' condition and probably the C class

>> should go first (built 2001/2). This means a horrible hole in the

>> procurement program.

>>

>> I can therefore only return to a solution that I have floated a few times

>> before, the lengthening of the A and/or B class. A new middle section for

>> the B class could be produced fairly cheaply by any competent bus builder,

>> and given the quality of Bustech's single deck buses (using parts made in

>> China!) it should be able to do the job. If Z cars are being scrapped,

>> there will be plenty of spare bogies for the extra articulation. The B

>> class need a thorough overhaul - rather like the current life extension

>> they are getting now. This should be able to give anything from 50 to 100

>> B3 class trams which would provide a partly low floor tram to last till

>> 2050. If W class can still be fixed to to near as new condition, it should

>> not be impossible to do the same to B class cars. Yes, I know that the W

>> cars had wooden bodies and effectively the rebuilt cars have completely new

>> bodies except for the brass fittings, but Melbourne does not have salt on

>> the roads which kills steel bodies.

>>

>> The A class cars need a low floor extension, by cutting off one end and

>> adding a low floor body, and then replacing the end. There would be a

>> bogie about half length of the extension, but this does not need to

>> swivel. In fact, it would be ideal for the wheels to be under the seats.

>> Usual seat spacing for facing seats in Melbourne is 1.5 m, thus seats would

>> happily cover the wheels for a 1.8 m wheelbase. Yaw problems as on the C

>> class are possible, but these should be eliminated by suitable springs and

>> dampers.

>>

>> This would give another 50 or so low floor trams and make possible the

>> complete provision of a low floor fleet by the 2032 deadline.

>>

>> Regards

>>

>> Dudley Horscroft.

>>

>>

>> On 28/11/2020 3:37 pm, Mal Rowe wrote:

>>

>> Victoria's DoT has been criticised in a damning report by the Victorian

>> Auditor General for lack of even a plan to meet disability access

>> requirements on trams.

>>

>> The report is at:

>> https://www.audit.vic.gov.au/report/accessibility-tram-services

>>

>> A pdf of the report is at:

>> https://www.audit.vic.gov.au/sites/default/files/2020-10/20201015-Accessibility-Trams-report.pdf

>>

>> VAGO says that: "DoT does not have conclusive plans for how it will

>> create an accessible tram network, 18 years after DSAPT was established.".

>>

>> The attached chart from the report shows what would be required to meet

>> the legislated targets of stops compliant by 31 Dec 2022 and trams

>> compliant by 31 Dec 2032 compared to current levels of progress.

>>

>> There's an interesting comment on p63 of the report: "An interactive

>> design process is underway for the Next Generation Tram involving major

>> rolling stock manufacturers who are working with DoT to design a tram that

>> will be suitable for Melbourne’s network, as well as meet DSAPT

>> requirements." In a later paragraph there is reference to the need for

>> funding in the 2020-21 budget to allow this to proceed - funding that is

>> now presumably in place.

>>

>> Mal Rowe - who sees this as a landmark report.

>>

>>

>>

>>

>>

>>