Re: Spanish Fleece hits the 'Late Rail
  Mal Rowe

On 21/02/2018 4:17 PM, Greg Sutherlandgregsutherland@... [TramsDownUnder] wrote:
>

> Page 1 Sydney Daily Telegraph 21 February 2018

>

Can't resist ...

I note that to achieve target the contractors would need to lay 260m of track per day per day.
Based on previous anouncements I am assuming that refers to single track  - i.e. 130m of double track per day.

The recent Lygon St relay was 4500m of double track over 13 days - a bit over 690m of single track per day.

Mal Rowe - acknowledging that could not be maintained over a longer period.