Adelaide Progress Cont'd.
  Rubberman92


The concreting of the special work now lacks only the last two curves. Asphalting is being done on the approaches, and overhead span wires are up over the intersection. So, with two and a half days to go, it looks like traffic will be flowing through the intersection on time.  Of interest is a set of traffic lights set back about 15m short of the intersection. The South facing lights are obviously just before the points, so the motorman sees them. However, the North facing lights on the other side of the pole are a question mark. Unfortunately,  I couldn't get a face on shot, but they do seem to be cycling with the other lights on the intersection as one can see the red/green glows changing.