The tracks are all in place in Toorak Rd West, but not yet levelled and
ready for concrete.
First view looks East from near St Kilda Rd - along the former slip lane
/ parking area.
http://tdu.to/East-to-ToorakRdWest_21Jun2017.JPG
Second pic is a little further east along the new track.
http://tdu.to/Kerb_ToorakRdWest_21Jun2017.JPG
This track is at the final level and a kerb is being installed to keep
motor cars off the tram tracks. This should improve punctuality a little.
Third pic is near the eastern end of the works looking back to the west,
and showing the new crossover at Millswyn St in place.
http://tdu.to/ToorakRdWest-at-MillswynSt_21Jun2017.JPG
This track will also be lifted - up to about the level of the access
cover in the centre of the pic.
Overall, the result will be quite a thick layer of concrete from current
excavated base up to the top of the sleepers - but nothing like the
current Sydney practice.
Mal Rowe - who can see that this change will bring some improvement to
route 58.