Re: Toorak Rd West progress
  Dudley Horscroft

Thanks Mal.

Regards

Dudley Horscroft
----- Original Message -----
From: "Mal Rowemal.rowe@... [TramsDownUnder]" TramsDownUnder@...>
To: TramsDownUnder@...>
Sent: Wednesday, June 21, 2017 9:17 PM
Subject: Re: [TramsDownUnder] Toorak Rd West progress [1 Attachment]


> On 21/06/2017 7:41 PM, 'Dudley Horscroft'transitconsult@...

> [TramsDownUnder] wrote:

>>

>> Thanks, Mal. Can you advise how the final alignment and levelling of

>> the track will be carried out - by machine and laser or by eye

>> and crowbar+ shovel?

>>

>

> A bit of both Dudley,

>

> The attached pic is a section of an earlier pic.

> http://tdu.to/Kerb_ToorakRdWest-detail_21Jun2017.JPG

>

> Just in front of each of the workers you will see that a section of rail

> is propped up on various bits of packing to get it level.

> That level was set with hand operated jacks.

> No doubt that level will have been measured with the latest laser

> levelling, but it's a man with a shovel who does the packing.

>

> Mal Rowe - pragmatic

>