GCLR 2 - first rails to be laid this weekend
  Richard Youl

The concrete track support slabs were previously laid across both directions of Napper Road in recent weekends. This is where the line leaves Smith St and turns north beside the QR rail line. It is one of only 2 road crossings on the entire extension.

There has been however quite a bit of rain over the last two weeks with little time to for the ground to dry out between wet days. Consequently there has been next to no earthworks taking place.

It was probably this job that was postponed from last weekend due to expected rain and even this weekend could have some very light rain but having lost nearly 2 weeks, I guess they are keen to keep going.

Regards,

Begin forwarded message:

> Subject: Napper Road & Olsen Avenue email update for this weekend.

>

> Good Afternoon.

>

> The information below is a reminder of what to expect this weekend from 8..00pm Friday 24 March until 5.00am Monday 27 March 2017 at Napper Road, Parkwood and upcoming weekend works at Olsen Avenue and Wintergreen Drive intersection.

>

> CLOSED TO TRAFFIC - FULL WEEKEND ROAD CLOSURE

> NAPPER ROAD AT SMITH STREET INTERSECTION, PARKWOOD

>

> This weekend, lengths of rail will be placed within the previously installed concrete slabs crossing Napper Road at Smith Street intersection. Napper Road, Parkwood will be closed to through traffic at Smith Street intersection and a detour will be in place. Please seek an alternative route.

>

> Access for through traffic on Smith between the M1 and Smith Street Motorway will be maintained.

>

> The map below is a guide to illustrate temporary lane changes during this weekend reconstruction stage.

> Dates of major lane closures

>

>

> 8.00pm Friday 24 March until 5.00am Monday 27 March 2017 (rail installation)

>

>

> This scheduled work depends on wet weather and site conditions and may be subject to change.

>

> Napper Road is closed to through traffic, detour in place.

>

>

> Gail Harris

> Senior Community & Stakeholder Advisor

>

>

> 32 Industrial Avenue, Molendinar QLD 4214

> T 1800 425 799

> Egclrstage2@...

> cpbcon.com.au

>

>

>

>

> Detour map – Napper Road/Smith Street intersection works

>

>

> FUTURE WORK: Friday 31 March – Monday 3 April

> OLSEN AVENUE AND WINTERGREEN DRIVE INTERSECTION, PARKWOOD

>

> Work to install the concrete track slabs across Olsen Avenue will commence from 8.00pm Friday 31 March until 5.00am Monday 3 April, weather permitting.

>

> All traffic movements will remain open, however, lanes will be reduced on Olsen Avenue, Wintergreen Drive and Parklands Drive and contra-flows will be in place.

>

> Motorists should expect delays and allow extra travel time.

>

> If you have any questions, please do not hesitate to contact the project community number on 1800 425 799 or reply to this email.

>

> Thank you for your continued patience.

>

> You can still find your way to the Arundel Plaza Family Fun Day by travelling via the local road network.

>

>

>

>

> G

> Gail Harris

> Senior Community & Stakeholder Advisor

>

>

> 32 Industrial Avenue, Molendinar QLD 4214

> T 1800 425 799

> Egclrstage2@...

> cpbcon.com.au

>

>

> ****************************************************************** This email, and any files transmitted with it, are confidential and intended for use by the addressee only. The confidential nature of the information contained in the email and/or file attachment is not waived, lost or destroyed if it is sent to other than the addressee. Use or dissemination of the information contained in the email and/or file attachment, by a recipient other than the addressee, may cause commercial damage to both/either the sender and/or addressee. If you are not the addressee of this email/file attachment contact the sender immediately and delete this email/file attachment. All email communications to and from this company are filtered and stored for risk management purposes in accordance with our Computer and Email Policies. Please contact our Privacy Manager on +612 8668 6947 if you would like further information about our Policies in regard to these issues. ******************************************************************

Show full size
image003  |  305W x 215H  | 8.83 KB |  
Show full size
image004  |  77W x 55H  | 2.08 KB |  
Show full size
image007  |  105W x 34H  | 1.88 KB |  
Show full size
image010  |  602W x 568H  | 32.89 KB |  
Show full size
image005  |  522W x 731H  | 363.16 KB |  
Show full size
image006  |  77W x 55H  | 2.08 KB |  
Show full size
image007  |  105W x 34H  | 1.88 KB |